Clean Water Program LogoCity of San Mateo LogoCity of Foster City LogoCity of San Mateo Public Works Logo

 

El Camino Real Sewer Capacity Improvements

Project Type: 

Conveyance – Basin 2-3 Collection System Improvements

Approximate Construction Start & End Dates:

Spring 2024 – Spring 2026

Project Status:

The El Camino Real Sewer Capacity Improvements Project is part of our 10-year plan to improve San Mateo’s overall wastewater system and better manage flooding.
The majority of the El Camino Real (ECR) Sewer Capacity Improvements Project was completed in December 2024. The project included installation of approximately 7,800 linear feet of pipe, including new and upsized relief sewers and maintenance hole installations.

All construction work in Areas 1 and 3 was completed as shown in the figure. As noted above, some work remains in Area 2 along El Camino Real The remaining work involves a section of sewer installation work near Laurel Creek that got delayed due to unforeseen underground conditions, and should be complete by Spring 2026.

The remaining construction near Laurel Creek will be performed during the night shift to minimize disruption to community. Work hours are Monday through Friday between 10 p.m. and 6 a.m.

Project Locations:

Work in Areas 1 and 3 is complete. The remaining project work will be performed in the Laurel Creek Siphon area shown in Area 2.

Separate notifications will be sent prior to the start of construction to alert property owners and occupants affected by this work.

Potential temporary construction impacts may include:

  • Parking restrictions and lane closures – only in work zones
  • Driveway access restrictions – only in work zones
  • Detours when working night shift on El Camino Real
  • Construction noise, vibration and dust
  • Potential sewer service disruptions – only for short duration
El Camino Real Areas 1, 2, and 3 location map.

Project Description:

The purpose of the Basin 2 & 3 Collection System Upgrade is to improve the ability of the overall wastewater collection system to manage sewer flows during heavy seasonal rainfall. During heavy rains, the wastewater collection system capacity is overwhelmed by the amount of rainwater that enters the system through infiltration and inflow. This causes sewer overflows at locations around San Mateo, such as at maintenance holes. These overflows contaminate city streets, creeks, lagoons, beaches, and the San Francisco Bay. The planned improvements will help prevent sewer overflows, as well as help the City comply with regulatory requirements.

The El Camino Real Sewer Capacity Improvements project involves installation of sewers that total approximately 7,800 linear feet of pipe, including new and upsized relief sewers and installation of manholes. The upgrades will reinforce the system with additional capacity, helping to reduce sewer overflows.

We thank you for your continued patience and cooperation as we near the completion of our sewer system improvements.

Key Project Contact:

CWP Project Manager: Makarand Pendse, 1-925-392-3726, Makarand.pendse@jacobs.com