Clean Water Program LogoCity of San Mateo LogoCity of Foster City LogoCity of San Mateo Public Works Logo

 

Underground Flow Equalization System

UFES Newsletter – November 13, 2020

UFES Shoring System Installation Begins Next Week

Construction on the UFES project will progress to Phase 2 starting next week, which includes installation of the shoring system equipment, excavation, and dewatering at the San Mateo County Event Center site. The upcoming work will include additional equipment and heavier construction at and around the Event Center. Ongoing underground utility locating activities will continue. Approved work hours are between 7 a.m. and 7 p.m. Monday through Friday.

Pipeline work along Saratoga Drive is anticipated to begin later this year. Prior to starting the pipeline work, a virtual community meeting will be held. Details will be provided once the date is set.

Please visit our UFES page  for more information, and to subscribe to receive UFES project updates as construction progresses. You can also e-mail info@CleanWaterProgramSanMateo.org, or call the UFES hotline at 1-650-522-7250.

Artist rendering of construction site at Event Center where activities will begin

The Latest on the County of San Mateo’s Health Orders

As the County of San Mateo’s COVID-19 Health Order continues to evolve, we follow all guidelines and safety instructions to ensure your infrastructure continues to improve during this time.