UFES Project Update – June 6, 2022
UFES Project is Making Great Progress
The UFES project continues to make great progress. Phase 5 construction is well underway, and includes installation of the mechanical and electrical equipment, concrete base, walls, columns, beams, and top slab for the UFES structure.
As of June 2, 2022, over 5,300 cubic yards of concrete have been poured at the at the Event Center Site. The floor of the underground concrete structure is complete. The next several concrete pours will build the walls of the structure.
The ongoing pipeline work along South Delaware Street will continue.
Pipeline work along Saratoga Drive has been suspended temporarily to accommodate events at the San Mateo County Event Center. All lanes in both directions will be open throughout June 2022. Traffic updates will be sent before the City has to close Saratoga Drive again in early July to continue with the pipeline work.
Traffic control measures remain in place. Signs are placed in specific areas to provide direction and ensure the safety of drivers.
Approved work hours are as follows:
San Mateo County Event Center Site: 7 a.m. – 7 p.m.; Saratoga Drive: 7 a.m. – 5 p.m.; South Delaware Street: 7 a.m. – 5 p.m.
*Construction schedules and traffic patterns are subject to change.
UFES project (looking southeast) showing completed floor and vertical wall forms; June 2, 2022
Stay Connected with the UFES Project
The Clean Water Program’s UFES construction is well underway and we want to keep you informed. The team established multiple information channels for residents and business owners to stay connected.
- Sign up for construction alerts (text the word UFES to 1-833-321-0231), email us at info@CleanWaterProgramSanMateo.org or call our hotline at 1-650-522-7250.
- You can also visit our UFES project page to see project details and sign up for our e-newsletter. If you don’t want to opt in, but still want information, bookmark the link where we post our updates to the project website.