UFES Work Hour Update – February 9, 2021
Night Work Now Approved for February 10, 2021
Due to anticipated wet weather on Thursday, after-hours work related to the UFES project (previously approved for Feb. 11) will now occur on Wednesday, Feb. 10. Work will include placing traffic control measures, such as road striping and signage adjustments, along Saratoga Drive between S. Delaware Street and E. 28th Avenue in preparation for pipeline construction. In an effort to alleviate impact on daytime traffic, work is scheduled to start in the evening on Wednesday, and will be complete Thursday morning. Nearby residents can expect minimal construction-related noise, dust, and vibration impacts from this work.
For more information, and to subscribe to receive UFES project updates as construction progresses, please visit our UFES page. You can also email info@CleanWaterProgramSanMateo.org, or call the UFES hotline at 1-650-522-7250.